Close Wine stage as accepted with known limitations
Maintainer decision, 2026-11-02: the core implementation and basic live behavior are sufficient for this stage. The original exhaustive done checklist was not fully satisfied and the contract is not marked Final; unfinished verification and known failures remain visible as future work.
This commit is contained in:
1 parent
5af9231822
commit
f44d0144bf
2 files changed
+62
-23
No files matched your search
@@ -131,7 +131,7 @@ At the start of every phase session:
|
||||
| 1 | Ready record, spawn evidence, mixed-prefix spawn semantics | `wine/ready-and-spawn-evidence` | `wine/ready-and-spawn-evidence` | Accepted and merged into `hunter` in both repositories; not pushed |
|
||||
| 2 | Live Wine settings | `wine/live-settings` | none | Accepted and merged into `hunter`; not pushed |
|
||||
| 3 | Wine preferences tab | `wine/preferences-tab` | none | Accepted and merged into `hunter`; not pushed |
|
||||
| 4 | Live verification and final results | `wine/verification` | Defect branch only for a proven helper cause | In progress; paused 2026-11-02 for further input; interim results fast-forwarded to `hunter`; not complete, not pushed |
|
||||
| 4 | Live verification and final results | `wine/verification` | Defect branch only for a proven helper cause | Closed by maintainer as accepted with known limitations, 2026-11-02; original checklist not fully satisfied; not pushed |
|
||||
|
||||
## Phase 0: native hook-exclusions foundation
|
||||
|
||||
@@ -430,11 +430,12 @@ regression in the same session.
|
||||
|
||||
## Phase 4: live verification and final results
|
||||
|
||||
Status: in progress; paused by the maintainer on 2026-11-02 for
|
||||
input from other folks before proceeding further. This is an
|
||||
interim freeze only: Phase 4 is not accepted or complete, and the
|
||||
contract is not Final. Contract decisions: 7, 8, 10, 11, 12, 14,
|
||||
15, 24.
|
||||
Status: closed by the maintainer on 2026-11-02 as accepted with
|
||||
known limitations, following the interim pause recorded below.
|
||||
The original exhaustive done checklist was not fully satisfied,
|
||||
and the contract is not Final. Contract decisions: 7, 8, 10, 11,
|
||||
12, 14, 15, 24, subject to the maintainer closure amendment in
|
||||
the contract.
|
||||
|
||||
Branch: `wine/verification` in Cthulhu, refreshed from `hunter`
|
||||
after Phase 3 has landed there. Open a narrow wine-access defect
|
||||
@@ -487,11 +488,13 @@ through `d6a54fc` plus this freeze record):
|
||||
mixed-prefix, keyboard-only preferences round trip, preliminary
|
||||
Braille movement/edit navigation, and basic Notepad++
|
||||
navigation/editing/Braille tracking.
|
||||
- Open and blocking until resolved or the maintainer amends the
|
||||
done criteria: the localized Wine window-title failure (no fix
|
||||
session or defect branch started yet); Battle.net login not
|
||||
reading, with investigation deferred by the maintainer; and
|
||||
completion of the physical-Braille pass, including menus.
|
||||
- Open at the pause and then superseded as closure gates by the
|
||||
maintainer's later accepted-with-limitations decision: the
|
||||
localized Wine window-title failure (no fix session or defect
|
||||
branch started); Battle.net login not reading, with
|
||||
investigation deferred by the maintainer; and completion of
|
||||
the physical-Braille pass, including menus. These remain real
|
||||
unfinished items, not passes.
|
||||
Cut, undo, menu return, copious Unicode, read-only mode, and a
|
||||
very long line in Notepad++ were not separately reported and
|
||||
are not claimed.
|
||||
@@ -539,6 +542,17 @@ Stop boundary: the stage is done only when every item in the
|
||||
contract's done checklist passes. Marking the contract Final is a
|
||||
separate maintainer act after those results are recorded.
|
||||
|
||||
Closure record, 2026-11-02: the maintainer superseded that stop
|
||||
boundary for this stage and closed it as accepted with known
|
||||
limitations, judging the original planning more expansive and
|
||||
pessimistic than the core objective requires. The delivered
|
||||
implementation and basic live behavior are accepted as working
|
||||
well enough. Unfinished verification and known failures remain
|
||||
visible in the contract and ledger as future work; they were not
|
||||
converted into passes. The contract was not marked Final, Phase 4
|
||||
was not represented as conventionally complete, and nothing was
|
||||
pushed by the master session.
|
||||
|
||||